Unless otherwise specifically set forth by the Planning Board in connection with its approval of a site plan, such approval shall expire if a building permit is not issued within one year from the date of approval and if all construction work is not completed within two years of the date of issuance of such permit. Upon application to the Planning Board, extensions totaling a maximum of 12 months may be granted to each of these time periods, for appropriate cause.