New Rochelle |
Code of Ordinances |
Part II. General Legislation |
Chapter 281. Streets, Sidewalks and Public Places |
Article III. Construction |
§ 281-44. Excavating and backfilling.
Latest version.
-
A.Excavated material. Excavated material shall be stored in neat piles, so placed as to cause the least interference with the use of the roadway or sidewalks. If so ordered by the Commissioner, such excavated material shall be promptly removed from the site of the work.B.Sheathing and shoring.(1)Except where the excavation is in rock and unless otherwise authorized by the Commissioner as provided hereinunder, tight sheathing at least two inches in thickness, securely fastened in place with whalers and braces throughout the duration of the work, shall be placed in all trenches having a depth in excess of five feet, shall be driven to the same depth as the lowest part of the pipe, conduit or structure proposed to be installed and shall be carried down in such a manner that the bottom of the sheathing shall at no time be more than one foot above the bottom of the excavation.(2)Whenever conditions make it necessary, the Commissioner may require that the sheathing be driven ahead of the excavation as the latter proceeds.(3)Unless otherwise authorized in writing by the Commissioner, sheathing and shoring shall be left in place with a cutoff line 18 inches below ground surface.(4)The Commissioner may, in his discretion, authorize that the use of sheathing and shoring be omitted in whole or in part if the horizontal distance from the edge of the proposed excavation to the nearest edge of the pavement or other surface or subsurface structure is not less than the vertical depth of the proposed excavation as measured from the highest point of such pavement or other surface or subsurface structure.C.Rock excavation.(1)In rock excavation, drilling and blasting shall be conducted with all possible care. All blasting operations shall be conducted in strict accordance with the existing ordinances and regulations relative to rock blasting and the storage and use of explosives. A blasting permit must be obtained from the New Rochelle Department of Fire in all instances.(2)Any rock excavation within five feet of a water or gas main, pavement or other surface or subsurface pipe, conduit or structure shall be done with very slight charge of explosive, and the utmost care shall be used to avoid disturbing or injuring said structure.(3)The permittee shall use the utmost caution in properly protecting all surface and subsurface structures from the effects of blasting, and any damage done to such structures shall be promptly repaired by the permittee or by such other parties as the Commissioner may direct, at said permittee's own expense.(4)Sufficient warning shall be given to all persons in the vicinity of the work before blasting. The site of the blast shall be covered with heavy timbers, blasting mats or other devices to prevent damage from flying rock fragments.(5)The time of blasting and the manner and size of charges must be satisfactory to the Commissioner. The blasting shall be done only by properly licensed individuals.(6)The permittee shall give adequate notice to the City and to the appropriate public service corporations before proceeding with blasting in the vicinity of water mains, sanitary sewers, stormwater drains and other drains or other public utility lines.D.Backfilling.(1)No backfilling shall be done by the permittee until the work being done under the permit shall have first been inspected and backfilling authorized by the Commissioner. In case of nonconformity with this requirement, the permittee shall forfeit the deposit, and the Commissioner shall have the authority to deny said permittee of any future permit.(2)The material used to backfill the bottom of the trench up to a level of two feet above the completed pipe or other structure shall be clean earth, sand or rock dust and shall contain no broken rock, stone or frozen earth.(3)Above a level two feet higher than the top of the completed pipe or other structure, the material used for backfill shall be approved material containing no frozen earth and not more than 1/3 broken rock, and no stone or piece thereof shall exceed 1/2 cubic foot in size.(4)The space between the pipe or other structure and the bottom and sides of the trench shall be packed full by hand and thoroughly tamped as fast as placed and up to the level of the top of the pipe or other structure, which shall then be covered by hand to a level of at least two feet higher than the top thereof, material being carefully deposited and tamped in layers not more than six inches thick.(5)Such tamping shall be done with a light tamper weighing from six to eight pounds and shall be conducted in such a manner as to secure compacted backfill without in any way injuring or disturbing the completed pipe or structure. At least one man shall be provided for tamping for each man engaged in backfilling.(6)Backfilling above the level of two feet above the top of the pipe or other structure shall be done in successive horizontal layers not exceeding one foot in depth, and each layer shall be thoroughly compacted by means of approved mechanical tamping equipment or by such other means as may be approved by the Commissioner.(7)The use of power equipment or other mechanical means for backfilling will not be allowed unless provision has been made for adequate compacting of backfill material, and then only with the prior written authorization of the Commissioner.(8)Compacting the backfill by means of flooding or puddling with water will not be allowed except with the prior written authorization of the Commissioner.E.Driving small pipes. Tunneling under pavements or sidewalks will not be allowed, but small pipes or conduits having a dimension of six inches or less may be driven beneath pavements or sidewalks in such a manner that the surface shall not be disturbed or injured, and provided that:(1)The prior written approval of the Commissioner is obtained.(2)No excavation in connection therewith shall be closer than one foot to the edge of a sidewalk or 18 inches to the edge of a pavement.(3)Such pipes or conduits shall be enclosed in sleeves or larger pipes so that required replacements or repairs may be made in the future without disturbance or injury to the pavement or sidewalk.(4)In the event of damage to a pavement, sidewalk or subsurface pipe or structure caused by driving such pipe or conduit, the permittee shall repair and make good the damage at the permittee's own expense.Editor's Note: Amended during codification; see Ch. 1, General Provisions.